EXECUTIVE SUMMARY

"A Safety Assessment for Proposed Pump Mixing Operations to Mitigate Episodic Gas Releases in Tank 241-SY-101: Hanford Site, Richland, Washington"

F. Biehl, W. Mirchler, T. Butler, R. Davidson, J. Edwards, S. Eisenhawer, R. Farman, S. Fischer, W. Kubic, R. Fujita, L. Goen, J. Hanson, R. Johnson, D. MacFarlane, K. Pasamehmetoglu, R.T. Perry, E. Rodriguez, D. Sanzo, J. Sapir, K. Sasser, N. Schnurr, D. Smith, J. Spore, R. Stevens, H. Sullivan, L. Trujillo, J. White, T. Wilson, C. Brown, L. Shephard, J. Teel, J. Holderness, S. King, G. Medford, C. Unal, J. Travis, D. Smith, and J. Clark




This safety assessment (SA) addresses each of the elements required for the proposed action to install, operate, and remove a mixer pump in Tank 241-SY-101, which is located within the Hanford Site, Richland, Washington. The proposed action is required as part of an ongoing evaluation of various mitigation concepts developed to eliminate episodic gas releases resulting in hydrogen concentrations in the tank dome space that exceed the lower flammability limit. In addition, the scope of this SA covers the installation, operation, and removal of the water-lance assembly (used during mixer pump installation) and the water wands (used during mixer pump removal). The installation, operation, and removal of the multiport riser, multiport flange, in situ viscometer, and voidmeter also are within the scope of this SA.

The pump was installed on July 3, 1993, and was tested through several phases of a test plan designed to slowly increase the pump's operating speed and duration. The test program was very effective in demonstrating that the mixer pump will minimize gas suspended in the waste and maintain the waste in the tank at a low level. The SA has been modified to take into account information learned in the test program. This process continues. This SA originally was written before installation of the mixer pump and contained tight restrictions on operations to prevent making the tank conditions worse than before mixer pump operations. As information has been gained through continued operations, new problems have been identified and have been addressed in this SA. This SA currently is in transition from covering the testing over a limited time span to continued long-term operations to keep the tank mitigated. We anticipate that in future revisions of the SA, the controls for operations will continue to be relaxed to promote more routine operations. Credit has been taken for the fact that the mixer pump appears to be effective in keeping the tank mitigated; however, this requires that the pump be operated routinely to mitigate the tank and prevent pump failures as a result of plugging.

In this SA, the potential hazards associated with the proposed action were identified and evaluated systematically. As new knowledge of the tank and pump system behaviors was gained, the SA was revised to incorporate new information. Several potential accident cases that could result in radiological or toxic gas releases were identified and analyzed and their consequences assessed. Administrative controls and procedures required to eliminate or reduce the potential of hazards were identified.

The majority of the accident sequences were evaluated using deterministic methods. The sequences were found not to result in radiological, toxic gas, or structural consequences that would cause a breach of the tank below the level of the waste. The load capacities of the pump structure, 42-in. tank riser, tank bottom, tank wall, tank dome, and pump pit were computed. The drop loads of the pump with the shock absorber installed were found to be within the capacity limit of the structures, provided that the procedural controls for pump lifting are maintained. The seismic and rollover loads were found to be within the capacity limits of the pump and tank. The misalignment loads associated with pump installation and removal were computed and compared with the riser capacity; controls and procedures then were developed to prevent unacceptable damage to the riser. The loads associated with missiles from a disintegration of the pump assembly were found to be within the capacity limits of the tank bottom and side wall. Criticality associated with the concentration of fissile material in the tank was examined and found to be impossible. The loads associated with a postulated hydrogen burn in the pump support column were found to be within the capacity limits of the pump support column. The structural loading associated with a hydrogen burn in the tank was found to be within the capacity limits of the tank structure, provided that the gas release is limited by procedural controls on pump operation.

Accident sequences that could result in either radiological or toxic gas releases were analyzed and found acceptable if activities were performed in accordance with approved procedures and specified administrative controls. These accident sequences consisted of the following:
  • gas releases and burns during pump installation or pump removal,
  • gas releases and burns during pump operation,
  • spills of radioactive material associated with contaminated pump removal,
  • release of radioactive material associated with a spray of waste outside the tank resulting in failure of pressure sensing devices, and
  • release of radioactive material associated with drops of a contaminated pump assembly.

  • Mitigation by mixing requires that the pump continue to be operated routinely to prevent excessive gas accumulation and to prevent plugging. If the pump fails and cannot be replaced, the tank could revert back to its unmitigated condition. In this case, we could experience gas releases, if ignited, that would result in tank failure. Mitigation of the tank using a mixer pump is not without risk; however, we believe, as demonstrated by this SA, that the risks associated with mixer pump operation are acceptable and are preferable to allowing the tank to revert back to its unmitigated state.

    LA-UR-92-3196, Rev. 12 (September 8, 1994)

    Return to Rick (Jenks) Johnson Home Page







































    KEYWORDS: nuclear engineering los alamos hanford waste tanks privatization twrs flying pilot telecommuting oregon thermal hydraulics TRAC simulation analysis code development necessary and sufficient standards telecommuting rick johnson nuclear safety transportation safety risk telecommute work option work from home radiation heat transport numerical analysis macintosh cray research review regulations telecommuting work option flexiforce safety telecommuting